The Evaluation Report of Project Proposal for the Xingfeng Street in Daxing District (April 1st, 2008)


The Invest Beijing International and Beijing Development and Reform Commission entrusted BOT Investment Co., Ltd. On March 26, 2008,? to evaluate the Project Proposal of the Xingfeng Street in Daxing District. Our corporation immediately established a project expert term, made preliminary preparations for the evaluation work and set down detailed work schedules.
On March 28, 2008, the evaluation and expert team visited the project spot in Daxing District to carry out investigation and held a appraisal meeting, followed by detailed communication and discussions with relevant project institutions relating to the concerned issues. After the comprehensive evaluation on the Project Proposal and the supplementary materials supplied by the project institutions, our corporation successfully completed the evaluation task on April 1, 2008, by submitting the document named ”°the Evaluation Report of the Project Proposal for the Xingfeng Street in Daxing District”± to Beijing Development and Reform Commission.
The construction scope of this project: The total road length is about 582m plus water supply and sewerage,Ӣelectric powerӢtelecommunicationӢgas project Ӣthe traffic projectӢvirescenceӢillumination etc. The gas project and the traffic project will be constructed by the professional company at the same time. The estimated budget is RMB 46.24million. It will take one year to complete.