As entrusted by the Invest Beijing International Co. as well as the Beijing Development and Reform Commission on July 4, 2008, BOT Investment Co., Ltd. undertook the evaluation of Funds Application Report for Beijing New BCP Sludge Drying Disposal Project. Our corporation immediately established a project expert term, made preliminary preparations for the evaluation work and set down detailed work schedules.
On July 7, 2008, the evaluation and expert team to the project spot to carry out investigation and hold a research meeting, followed by detailed communication and discussions with relevant project institutions about the questions. After the comprehensive evaluation on the Item Funds Application Report and the supplementary materials supplied by the project institutions, our corporation successfully completed the evaluation task on July 11, 2008, by submitting the document named ¡°the Evaluation Report of Beijing New BCP Sludge Drying Disposal Project Item Funds Application Report¡± to Beijing Development and Reform Commission.
The main scope of this project: construct a new disposal center of 500t/day sludge drying disposal capability. The total area is 3266 ©O,and the area of structure is 3100 ©O. After the evaluation, the adjusted budget of this project is RMB 150.72 million. |